Sunday, June 04, 2006

June 2 2006 Site Visit












Monday, February 27, 2006

February 26 Site Visit









Interior Wall separating Automatic and Self Serve areas installed. Heat is being poured into the building to allow for development of underslab piping and sumps.

Wednesday, February 08, 2006

February 5 Site Visit

Exterior Cladding is mostly complete and interior insulation follows quickly behind.
Overhead doors are noticeably larger both in width and height as compared to the Fort Car Wash, to maximize vehicle capacity.
Heat will be poured into the building upon Exterior Cladding completion to thaw out the floor. Piping and Sump placement will occur inside and then floor will be poured. Once the floor has cured, the mechanical, electrical, and equipment installations can all take place.





Monday, January 16, 2006

January 15 2006 Site Visit





Structural Steel is being Erected:

Thursday, January 05, 2006

December 27 Site Visit

As learned during the Fort Car Wash construction, only galvanized materials are to be used to ensure that rusting and decay of the structural members can be minimized.

Galvanized Structural Steel on Site:


Galvanized Anchor Bolts:


Grade Beams have been poured, waiting for building erection.

Automatic Bay (CN Land in background):


Vending Area (in the background you can see the CN Land):

Self Serve Bays:


Thursday, December 22, 2005

December 1 Site Visit


Thursday, December 15, 2005

November 15 Site Visit

Construction Update:
Fence Erected and grass/ weed growth controlled.
Piling complete.